how do you find the mean completion time of a PERT network diagram?​

Respuesta :

okekesarah01642112
okekesarah01642112 okekesarah01642112
  • 02-01-2021

Answer:

PERT is an estimating technique that uses a weighted average of three numbers (see below) to come up with a final estimate. The resulting PERT estimate is calculated as (O + 4M + P)/6. This is called a "weighted average" since the most likely estimate is weighted four times as much as the other two values.

Answer Link

Otras preguntas

What is the basic difference between the andes and the other highland regions of south america?
Would a year on the planet Neptune be longer or shorter than an earth year? Explain
which of the following people would be a member of the Europe middle class following the industrial revolution
is 400 pints greater than less than or equal to 100 gallons
the square root of 100 over 4x squared
Can someone pls help me with this.. Thanks in advance
why do you think tact is an important quality?
Translate the sentence into an equation. Four times the difference of a number and 5 is equal to 8. Use the variable w for the unknown number.
Who built the worlds first liquid-fueled rocket? Robert Goddard Konstantin tsiolkovsky Hermann oberth Neil Armstrong
36 pounds decreased by 75%